Friday, June 19, 2015

1908 Shattuck - Construction Update 5

The past couple of weeks at the 1908 Shattuck construction site, the main focus has been the framing of the second floor, and the installation of the third floor joists. The runnel has been poured, and the CMU has been installed in the North wall. The next stages are the framing of the third floor and the grading around the buildings perimeter. From the opposite side of the street, you can now get a real sense of what the street will look like when the project is complete.